Free-Issue Materials in GCC Construction: How to Track Owner-Supplied Items Without Losing Accountability - Blog
Free-Issue Materials in GCC Construction: How to Track Owner-Supplied Items Without Losing Accountability

July 24, 2026

Free-Issue Materials in GCC Construction: How to Track Owner-Supplied Items Without Losing Accountability

Ahmed ElazabAhmed Elazab

The Problem Nobody Talks About

On a SAR 300M Aramco project, the client supplies 40% of the project value directly — structural steel, pumps, valves, instrumentation. The contractor receives it, stores it, installs it, and hands it back in the finished asset. But if the contractor cannot tell the client how many pump sets are in the laydown area, how many were installed, and what happened to the two that arrived damaged, the contractor carries the financial liability for items it never bought.

This is the free-issue materials problem. It is common on GCC construction projects, it causes real financial exposure at final account, and most contractors manage it with a paper logbook that nobody maintains after month two.

What Are Free-Issue Materials?

Free-issue materials — also called employer-supplied materials, owner-furnished equipment, or client-furnished materials — are items the client procures and delivers to the contractor's site for installation. The contractor does not buy them, but takes custody and becomes fully responsible for storage, handling, protection, and installation.

On GCC construction projects, free-issue materials appear most often on:

  • Aramco projects: Process equipment, instruments, and specialty piping sourced through Aramco's own procurement system
  • NEOM projects: Proprietary architectural and technology elements from approved global suppliers
  • ROSHN projects: Mechanical, electrical, and fit-out packages specified and sourced centrally
  • Government infrastructure: Transformers, switchgear, and telecoms equipment supplied by client utility departments

The scale varies. Free-issue might be a handful of specialty valves — or SAR 35M worth of pumps and piping on a process plant. Either way, the contractor installs it but never owns it, and must account for every unit from first receipt to final handover.

Why Free-Issue Materials Go Wrong

The problem is not the concept. It is that most contractors treat free-issue materials as a site admin task rather than a commercial obligation. Three failure modes repeat across GCC projects:

No Receipt Documentation

Materials arrive, the storekeeper signs the delivery note, and the document disappears into a drawer. There is no record of what was received, in what condition, or in what quantities. When the client requests a free-issue reconciliation at final account — and FIDIC Clause 4.20 requires one — the contractor has nothing to produce.

Mixed Storage with Contractor-Supplied Materials

Free-issue valves stored alongside purchased valves of the same specification. When installation starts, no one can tell which is which. The contractor ends up buying replacements for free-issue items consumed in error, or faces accusations of misappropriation. Both outcomes are expensive.

No Reconciliation Report

At completion, the client expects a formal account: units received, units installed, units returned, units damaged. If the contractor cannot produce this, FIDIC Clause 4.20(d) places full liability for unaccounted items on the contractor. On a SAR 40M free-issue package, a 2% accountability gap is SAR 800,000 of exposure — on items the contractor never purchased.

FIDIC Clause 4.20 — What It Actually Requires

FIDIC 2017 Clause 4.20 sets out the contractor's obligations explicitly:

  • Inspection on delivery. The contractor must inspect materials on receipt and report any shortages, defects, or damage to the Engineer promptly — typically within 48-72 hours for Aramco projects.
  • Safe storage. The contractor is responsible for protecting free-issue materials from loss, damage, or deterioration from receipt until incorporation into the permanent works.
  • Exclusive use. Free-issue materials may only be used on the project they were supplied for. Using client-supplied materials on an adjacent project is a breach of contract and potentially a criminal matter.
  • Reconciliation. The contractor must account for all quantities: installed, remaining in store, returned, and damaged — with supporting documentation for any loss.

For Aramco projects, SAEP requirements add tagging, traceability, and material test certificate (MTC) tracking that must accompany each item through installation.

What a Proper Free-Issue Tracking System Looks Like

Free-issue materials need a parallel track alongside the standard inventory system — because they never enter accounts payable, but they are physically on site and legally the contractor's responsibility.

The Free-Issue Receipt Register

Every delivery requires a register entry with at minimum:

  • Material description and tag or item number
  • Quantity received and unit (each, tonnes, metres)
  • Condition on receipt: Good / Minor Damage / Major Damage, with photograph
  • Delivery note or packing list reference
  • Date received and storage location (laydown zone reference)

For Aramco: add the Aramco Material Number, MTC reference, and heat number for piping or structural steel.

The Consumption Tracking Log

When free-issue materials are issued for installation, the system records the date, quantity, work order reference tied to the specific BOQ activity, and who it was issued to. This creates a running balance: received minus issued equals remaining in store. Any variance should trigger immediate investigation — not a month-end reconciliation exercise.

The Damage and Shortage Report

Damage reports must be issued within the contract timeframe, addressed to the Engineer, and include a description with photographs, quantity affected, assessment of cause, and a request for replacement where programme demands it. Delayed reporting is the single biggest cause of rejected damage claims — clients argue the damage occurred on site under the contractor's custody. Reports must be contemporaneous.

The Financial Accounting Challenge

Because free-issue materials do not flow through accounts payable, they do not appear in the cost report. The project looks cheaper than it is — and true margins become impossible to calculate.

For management accounting, free-issue materials must be reflected in the cost report:

  • Record the agreed value (from the client's BOQ or free-issue schedule) as a cost against the relevant WBS cost codes
  • Offset with a corresponding "employer-furnished materials" credit at the same value
  • Net impact on profit is zero — but the cost report now shows true resource consumption

For a SAR 200M project where the client supplies SAR 40M in electrical equipment, ignoring free-issue means the cost report shows SAR 160M consumed when SAR 200M of resources have been deployed. The project manager sees a 20% buffer. There is none. The EAC is wrong, and the margin call comes at final account.

The Claims Dimension

Free-issue materials create two valid claims scenarios that GCC contractors routinely miss:

Delayed delivery. If the client fails to deliver by the agreed date and this delays the works, the contractor has a FIDIC Clause 8.5(b) entitlement for an extension of time and potentially a cost claim under Clause 20.2. But only if a notice was issued within the Clause 20.2.1 window (usually 28 days) and contemporaneous records show the programme dependency. Without both, the entitlement is lost.

Defective delivery. If free-issue materials arrive in a condition requiring additional handling, inspection, or re-sourcing, the contractor may have a variation entitlement. The supporting records — damage reports, Engineer correspondence, programme impact — must be contemporaneous to carry weight with the Engineer or a DAAB panel.

Five Starting Steps

  1. Establish a free-issue schedule at contract award. Agree with the client before mobilisation: item list, delivery schedule, point of receipt, condition assessment process, and reconciliation format. Get it confirmed by the Engineer in writing.
  2. Designate a physically separated storage area. Even on constrained sites, segregation is non-negotiable. Free-issue materials go to a dedicated zone with clear signage. Mixing is the single biggest cause of irresolvable reconciliation disputes.
  3. Link every receipt to a BOQ activity. When the pump arrives, log it against the activity that requires it. The programme team knows material is on site. The QS knows the free-issue value has landed. The storekeeper knows which work order to issue against at installation.
  4. Issue damage reports within 72 hours. Set an internal deadline of 24 hours from discovery to report issuance. Anything later creates a credibility problem with the Engineer and may void the entitlement entirely.
  5. Reflect free-issue values in the cost report. Set up the WBS cost codes and offset credit before the first delivery arrives — not at month-end when the finance team discovers the gap.

The Bottom Line

Free-issue materials are a commercial obligation masquerading as a site logistics task. On Aramco, NEOM, and ROSHN projects, the values involved are not marginal — SAR 20M to SAR 50M of employer-supplied materials on a single contract is common.

The contractor that manages free-issue with a proper receipt register, physical segregation, consumption tracking, and timely damage reports closes projects with clean reconciliations and legitimate delay claims. The contractor that manages it on a shared spreadsheet no one updates faces disputed final accounts, rejected delay claims, and liability for items it never purchased.

The tracking system costs nothing to set up. The disputes it prevents cost significantly more than that.

Did you enjoy reading this blog? Share it

Ready to find out more?